Construction Facilities, IDC and Drawdown Order: When More Interest Can Still Create Equity Value
There are three ways to fund a construction budget: equity first, pro rata, or debt first with equity committed at the end. Sponsors are often told that equity-first is the conservative choice and debt-first is aggressive, because debt-first accumulates more interest during construction.
That is true and it is the wrong conclusion. On a $250m project over 24 months:
Equity first IDC + fees $11.69m Equity PV outflow $59.06m
Pro rata IDC + fees $13.63m Equity PV outflow $55.27m
Debt first IDC + fees $15.58m Equity PV outflow $51.60m
Debt-first costs $3.89m more in interest and commitment fees. It saves $7.46m of equity present value, because the equity cheque is written on average fourteen months later.
Net gain in this worked example: $3.57m. The direction follows from the assumed rate spread and timing, but it is not a universal rule. A lender can price earlier debt draws through margin, commitment structure, sponsor-support requirements, LC usage or a different equity-funding covenant, and those terms can change the answer.
This post covers how a construction facility actually works, how IDC is computed, why the drawdown order is a returns decision rather than a prudence decision, and where the circularity comes from.
ℹ️ Note: All figures are labelled assumptions, on a cosine S-curve drawdown profile. The direction of the result is robust; the magnitude depends on the spend profile and the rate spread.
What Is a Construction Facility?
A construction facility is a committed source of project-cost funding drawn under borrowing conditions and construction-control mechanics. Some facilities convert into term debt at a defined conversion date; others refinance into a separate term loan. A 2026 project financing, for example, provides construction loans and tax-credit bridge loans used for project costs, with term loans repaying the construction loans. Another 2026 project facility converts construction borrowings upon satisfaction of specified completion conditions.
During construction, operating cash flow may be absent or immaterial and the lender relies heavily on budget control, construction progress, sponsor support, security, project contracts and independent-engineer certification. Some facilities also have pre-completion revenues or other interim cash, so “no revenue” should not be treated as a universal rule.
How Does the Drawdown Actually Work?
Four mechanisms, each of which can delay money.
An availability period. The facility can be drawn only during the contractual availability period. A filed SunPower construction facility defines that period from satisfaction of borrowing conditions until the earlier of construction-loan maturity or earlier cancellation / expiry of commitments.
Conditions precedent, initial and recurring. The first drawing and later borrowing requests each have conditions set by the facility agreement. Filed construction facilities commonly require items such as no continuing default, repeated representations, requisition support, budget / project-cost evidence and satisfaction of specified project conditions, but the exact list must come from the documents.
Certification. Filed solar financings require borrower requisitions, invoices and independent-engineer certificates, and can require evidence that available construction funds plus equity commitments are sufficient for remaining project costs. That forward-looking sufficiency test is the practical cost-to-complete control.
Milestone linkage. Drawings are matched to construction progress rather than to an agreed calendar, which means a delayed project draws later, incurs less IDC, and — as the delay LD posts in contracts and legal material set out — may still be paying damages on four different clocks.
What Is IDC?
The interest accruing on drawn amounts during construction, capitalised into project cost rather than expensed.
Capitalisation is the natural treatment because there is no revenue to pay interest from. The cash is either funded from the facility itself — a drawing to pay interest on earlier drawings — or from a dedicated interest reserve, and either way it increases the amount ultimately outstanding.
Two consequences follow, and both matter more than the accounting.
IDC is part of the project cost that the gearing test applies to. More IDC means a larger project cost, which on a debt-to-capital test means a larger facility, which means more IDC. That is the construction-phase circularity the sculpting post identified as a loop separate from the operating sculpt — and one that is genuinely algebraic rather than an artefact of how the model was built.
IDC is a real cost, not a timing item. It is capitalised, financed, and repaid with interest over the term. A project with $15.6m of IDC has $15.6m more debt outstanding at commercial operation than one with none, and that additional balance consumes coverage for the life of the facility.
Commitment Fees: The Offset
The reason the trade is not one-sided.
A commitment fee may accrue on some or all undrawn commitments at the contractual rate. A structure that draws debt later can therefore carry more undrawn-fee cost even while reducing IDC. Use the facility's actual fee base and rate.
That produces a partial hedge against the IDC effect, visible in the worked numbers:
| Order | IDC | Commitment fee | Total |
|---|---|---|---|
| Equity first | $9,382,003 | $2,306,615 | $11,688,618 |
| Pro rata | $11,679,687 | $1,953,125 | $13,632,812 |
| Debt first | $13,977,372 | $1,599,635 | $15,577,007 |
The fee moves in the opposite direction to IDC and is smaller — about 15% of the IDC swing on these assumptions. So the net financing cost still rises as debt is drawn earlier, but by less than the interest alone suggests.
Worth noting: the commitment fee is the reason a facility sized generously "for comfort" is not free. An oversized construction facility that is never fully drawn pays fees on the unused portion for the whole availability period, and that cost is real.
The Three Orders, and What They Actually Trade
| Equity first | Pro rata | Debt first | |
|---|---|---|---|
| Lender comfort | Highest | Standard | Lowest |
| IDC + fees | $11.69m | $13.63m | $15.58m |
| Weighted avg equity month | 5.7 | 12.5 | 19.3 |
| PV of equity outflow | $59.06m | $55.27m | $51.60m |
| Net benefit vs equity first | — | $1.85m | $3.57m |
| Requires | Nothing | Nothing | Sponsor credit |
The last row is the constraint. Debt-first works only where the lender will accept a promise instead of cash — an equity commitment agreement from a creditworthy parent, or a letter of credit securing the contribution. A developer without that covenant cannot access the structure, however good the arithmetic.
That makes the drawdown order one of the few structural terms where sponsor balance sheet strength converts directly into project returns, independent of anything about the project itself. Two identical assets built by different sponsors will have materially different equity IRRs because of it.
What Happens If the Budget Is Exceeded?
A layered set of answers, and the order in which they are consumed is itself a structure.
Contingency is a budgeted risk allowance whose amount and draw controls are transaction-specific. Filed credit agreements can require the independent engineer to review the adequacy of proposed construction contingency and can prevent commitment reductions where remaining available construction funds would no longer cover remaining costs, including contingency.
A cost overrun facility may sit above it in some structures, while other deals rely directly on sponsor equity, subordinated support or additional committed funding. Do not assume a separate overrun tranche exists.
Sponsor support can be the ultimate backstop, but its form and amount are document-specific. Filed project agreements expressly count additional capital contributions or creditworthy funding commitments as Available Construction Funds. The financing value of the support therefore depends on the legal commitment and the credit behind it.
The cost-to-complete test is what forces all of this to happen at the right time. Each drawing requires a certificate that the remaining available funds are sufficient to complete the works. A project that fails it cannot draw — and the remedy is for the sponsor to inject the shortfall, restoring the test before construction can continue.
That test is worth understanding as the real completion covenant. It is forward-looking, it is certified by a third party, and it bites long before any physical milestone is missed. A project whose contingency is being consumed faster than its progress is, on this test, already in trouble — which is why contingency drawdown rate against percentage completion is one of the more useful things to monitor during construction, and one of the less commonly reported.
What Is Completion, and Who Certifies It?
Two different completions, and the distinction decides when the sponsor's support falls away.
Physical completion is the construction contract's concern — mechanical completion, substantial completion, commercial operation, as the first contracts and legal post set out. It is certified under the EPC contract and triggers the contractor's obligations and liabilities.
Financial completion, sometimes called project completion or term conversion, is the financing's concern. It is a defined set of tests in the credit agreement, and satisfying it converts the construction facility to the term facility and releases the sponsor's completion support.
Financial-completion / conversion conditions are document-specific. Filed project agreements include items such as Substantial Completion, delivery of term-loan borrowing requests, updated independent-engineer and insurance-adviser reports, required project documentation, reserve or model conditions and no default. Build the conversion checklist directly from the agreement.
Two observations.
Financial completion can lag physical completion substantially. A project can be generating and selling power for months while a reserve remains unfunded or a performance test remains to be repeated — and throughout that period the sponsor's completion guarantee is still live, which is a contingent liability with a cost even when nothing goes wrong.
The projected coverage test is the one to watch. It is the first point at which the assumptions from market structure material — basis, curtailment, capture rate — are applied to a real operating asset with real data, by a lender with an incentive to be conservative. A project that cleared its sizing test on the sponsor's case in 2024 may not clear its completion test on the lender's case in 2027, and the consequence is that completion support does not release.
How Is Interest Fixed During Construction?
A separate question from the drawdown order, and one with its own timing problem.
Many construction financings use floating-rate debt and can require interest-rate hedging under defined hedge ratios, dates and approved instruments. Where hedging is required, the challenge is matching hedge notional and timing to a drawdown profile that is still a forecast.
Two structures address it. A forward-starting swap fixes the rate now for a notional schedule that begins later, matching the projected drawdown and term amortisation. An amortising swap with a drawdown schedule follows the projected balance throughout.
Both carry the same risk: if the project draws slower than projected — which a delayed project does — the hedge is over-notional, and the borrower is hedging debt it has not drawn. Over-hedging is an exposure, not a conservatism, and it generates a mark-to-market position that has to be settled or carried.
The practical instruction is to size the hedge against a delayed drawdown case rather than the base case, and to retain the flexibility to increase it later. The asymmetry favours it: being under-hedged costs floating exposure on the increment, which is a manageable risk; being over-hedged means paying fixed on money that was never borrowed.
The Economic Rule in the Worked Example
Deferring equity creates value when the present-value benefit of later equity funding exceeds the incremental financing cost and any extra credit-support cost.
In the worked example, the project pays 6.5% plus fees to defer capital valued at a 12% equity discount rate. That spread drives the result, subject to the actual lender pricing and support package.
Value of deferring $1 of equity by one year
≈ Equity_Rate − (Debt_Rate + Commitment_Fee_Effect)
≈ 12.0% − 7.0% ≈ 5.0%
On $62.5m of equity deferred by roughly fourteen months, that approximation gives about $3.6m — which is the net benefit computed properly above. The rule of thumb is reliable enough to run in a meeting.
Two qualifications. It assumes the lender is indifferent, which it is not — debt-first shifts risk onto the lender and may be priced for. And it assumes the equity discount rate is a genuine opportunity cost rather than a hurdle rate chosen for convenience; where a sponsor has no alternative use for the capital, the benefit of deferral is smaller than the rate implies.
The first qualification deserves a number, because it bounds the whole argument. If a lender responds to a debt-first structure by widening the construction margin, the question is how much widening consumes the $3.57m benefit. On $187.5m drawn over an average of roughly ten months of exposure, twenty-five basis points costs on the order of $390,000 — so the benefit survives a great deal of repricing before it disappears.
That asymmetry is the practical reason to ask for the structure even where it will be priced. A sponsor offered debt-first at plus twenty-five, or equity-first at the original margin, should take the first without much deliberation. It is only at a hundred basis points or more of widening, or where the lender demands additional security for the equity commitment that costs the sponsor elsewhere, that the arithmetic becomes genuinely close.
How Do You Model This in Excel?
As a monthly drawdown schedule with IDC accruing on the opening balance and fees on the undrawn commitment, and with the equity timing effect reported alongside.
The monthly loop
For each month:
Spend(m) = S-curve × Total_Cost
Equity_Draw(m) = per drawdown order
Debt_Draw(m) = Spend(m) − Equity_Draw(m)
IDC(m) = Opening_Debt(m) × Monthly_Rate
Commitment_Fee(m) = (Facility − Opening_Debt(m)) × Monthly_Fee_Rate
Closing_Debt(m) = Opening_Debt(m) + Debt_Draw(m) + IDC(m)
Note that IDC accrues on the opening balance, not the closing one. Accruing on the closing balance charges interest on money drawn during the period for the whole period, which overstates IDC by roughly half a month's interest every month — a systematic error of around 4% of total IDC on a 24-month build.
The two outputs to report together
PF_TotalIDCAndFees equity first = $11,688,618
pro rata = $13,632,812
debt first = $15,577,007
PF_EquityOutflowPV equity first = $59,056,752
pro rata = $55,265,104
debt first = $51,595,361
PF_NetBenefit pro rata = $1,847,454
debt first = $3,573,002
Reporting IDC alone makes equity-first look best. Reporting both makes the actual trade visible, and it is the opposite conclusion.
The circularity, kept separate
Project_Cost = Construction + IDC + Fees + DSRA + Development
Debt = MIN( Gearing × Project_Cost , DSCR-sized )
IDC = f(Debt drawdown profile)
This loop is genuine and it is algebraic — solvable in closed form for a given drawdown profile, or by a small number of controlled iterations. Keep it separate from the operating-phase sculpt, which as the earlier post established is not circular at all.
ℹ️ Note: Model the S-curve, not a straight line. A linear spend profile understates IDC in the second half of construction, where most spend occurs and most of the balance is outstanding. On a cosine S-curve the difference is a few percent of IDC — small, but it is a free correction.
To build the monthly drawdown, IDC and fee schedule with the three drawdown orders compared, prompt Dezzmond with your construction budget and spend curve.
What Do Sponsors and Lenders Actually Check?
- What drawdown order applies, and has the net benefit of each been computed?
- Is the sponsor's covenant good enough to support a debt-first or deferred equity structure?
- Does IDC accrue on the opening balance? Closing-balance accrual overstates it systematically.
- Is the spend curve an S-curve or a straight line?
- What does the commitment fee cost on the facility as sized, and is the facility oversized?
- Is the construction circularity solved separately from the operating sculpt?
- What happens to the availability period if the project is delayed, and what does an extension cost?
Frequently Asked Questions
What is IDC?
Interest during construction — interest accruing on drawn amounts before the project generates revenue. It is capitalised into project cost rather than expensed, funded either from the facility itself or from an interest reserve.
Why does the drawdown order matter?
Because it determines when equity is committed. In the worked assumptions, drawing debt earlier defers the equity cheque and the present-value benefit exceeds the extra IDC and fees. Change the lender pricing, support costs or equity opportunity cost and the ranking can change.
How much is deferring equity worth?
Approximately the spread between the equity discount rate and the all-in debt cost, per year of deferral. On the worked case, deferring $62.5m by fourteen months at a 5% spread is worth about $3.6m, net of the additional IDC and fees.
What is a commitment fee?
A fee accruing on the undrawn portion of the facility. It moves in the opposite direction to IDC — drawing late means paying more in fees — and partially offsets the IDC saving from a late drawdown, by about 15% on the worked numbers.
What is the cost-to-complete test?
A certificate, required for each drawing, that the remaining available funds are sufficient to finish the works. It is forward-looking and bites before any physical milestone is missed, which makes contingency drawdown against percentage completion one of the more useful construction metrics.
What is financial completion?
A defined set of financing tests — commercial operation certified, performance tests passed, reserves funded, a projected coverage ratio met, no default — which converts the construction facility to term and releases the sponsor's completion support. It can lag physical completion by months.
Why can't every sponsor use a debt-first structure?
Because the funding order is negotiated and can require enforceable equity commitments, letters of credit or creditworthy sponsor support. A filed 2026 project arrangement, for example, permits construction-loan availability to affect when equity contribution requests are made, rather than applying one universal funding order.
Closing: The Conservative Structure Is the Expensive One
Equity-first funding is described as prudent, and from the lender's point of view it is — the sponsor's money is at risk before any of the bank's, which is exactly the position a credit committee wants.
In the worked example, equity-first has the lowest financing-cost line but the earliest equity funding, producing the lowest sponsor present value among the three assumed funding orders. That is a result of the example's rate spread and timing, not a universal ordering.
That is a useful modelling discipline for the series: structural terms often have a visible contractual cost and a separate timing or optionality effect that can point in the other direction: the waterfall position that raises leverage and lowers real coverage; the sweep that reduces debt and destroys equity value; the lock-up that protects the lender at a cost priced in deferred distributions; and now the drawdown order whose interest saving is smaller than the timing cost it creates.
The discipline is the same in every case. Compute both sides, report them together, and let the decision be made against the net figure rather than against whichever half happens to appear in the financing cost table.
the next post takes the moment this facility ends: term conversion, what has to be true for it to happen, and the refinancing risk sitting behind a mini-perm.
Sources: 2026 SEC-filed Project Swift credit agreement — construction and bridge proceeds fund Project Costs; term loans repay construction loans · 2026 Project Granite filing — construction-to-term conversion on specified completion conditions · SEC-filed SunPower construction credit agreement — construction budget, independent-engineer requisition and sufficiency of construction funds / equity commitment · 2026 Project Granite credit agreement — remaining costs, available sources and independent-engineer support for borrowings · Dezzmond analysis; worked-example funding orders are illustrative.